Prince2 Foundation Exam Test – 56

Which statement about the Directing a Project process is FALSE?

A. Supports the PRINCE2 principle of manage by exception
B. Is triggered by a request to initiate a project
C. Covers the day-to-day activities of the Project Manager
D. Provides a mechanism for the Project Board to assure that there is continued business justification

Correct Answer: C

Prince2 Foundation Exam Test – 55

What process is used by the Project Manager to maintain focus on delivery of a stage’s products within agreed tolerances?

A. Directing a Project
B. Controlling a Stage
C. Managing a Stage Boundary
D. Managing Product Delivery

Correct Answer: B

Prince2 Foundation Exam Test – 54

Which is a purpose of a Project Product Description?

A. Form part of the Work Package for the project product
B. Provide the initial project budget to be refined in the Business Case
C. Document the project mandate and gain approval for the project from the Project Board
D. Define the quality required of the project’s product

Correct Answer: D

Prince2 Foundation Exam Test – 50

Which statement about stages is true?

A. Management stages should be of the same duration
B. The use of technical stages is mandatory
C. The use of management stages is mandatory
D. Management stages are driven by specialist teams

Correct Answer: C

Prince2 Foundation Exam Test – 49

Which of the following statements about customer’s quality expectations and acceptance criteria are true?

1.Customer’s quality expectations form a specific and precise list of Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

2. Measurable criteria that a project product should meet in order to be acceptable to key stakeholders.

A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true

Correct Answer: D

Prince2 Foundation Exam Test – 48

Which is a purpose of the Controlling a Stage process?

A. Produce a Team Plan for the work to be assigned to a Team Manager
B. Select and implement actions that will resolve deviations from a plan within tolerance
C. Obtain approvals for products delivered in a Work Package
D. Update a Project Plan to incorporate the actuals from a Stage Plan

Correct Answer: B