Prince2 Foundation Exam Test – 46

Which is assumed to be a supplier’s responsibility in the PRINCE2 customer/supplier environment?

A. Specify the desired result
B. Provide the resources and skills to deliver the desired result
C. Pay for the project
D. Specify the benefits of the project

Correct Answer: B

Prince2 Foundation Exam Test – 45

Which is a purpose of a Project Brief?

A. Capture lessons from previous projects
B. Ensure that there is a common understanding of the starting point for the project
C. Confirm that the Project Plan is able to deliver the Business Case
D. Define the quality techniques and standards to be applied during the project

Correct Answer: B

Prince2 Foundation Exam Test – 44

Who is the key project decision-maker in the project management team?

A. Corporate management
B. Executive
C. Change Authority
D. Project Manager

Correct Answer: B

Prince2 Foundation Exam Test – 43

Which is a purpose of the Business Case theme?

A. Identify which role is responsible for producing the Business Case
B. Identify the project’s outputs
C. Establish the controls to manage changes that may impact the project benefits
D. Establish a viable investment proposition


Correct Answer: D

Prince2 Foundation Exam Test – 42

Which is a purpose of a Product Description?

A. Provide the cost tolerance available for individual products
B. Define reporting frequency
C. Record the quality checks completed for the End Stage Report
D. Document the level of quality required of a product

Correct Answer: D

Prince2 Foundation Exam Test – 41

Which is a purpose of a Project Product Description?

A. Records the costs and timescales for delivery of the project’s final product
B. Shows the dependencies between the project’s products to aid planning
C. Provides a list of all the products to be delivered by the project
D. Defines what the project must deliver in order to gain acceptance

Correct Answer: D

Prince2 Foundation Exam Test – 40

How should the Team Manager report that tolerances are forecast to be exceeded?

A. Create an Exception Report
B. Create a Highlight Report
C. Raise an issue
D. Grant a concession

Correct Answer: C

Prince2 Foundation Exam Test – 39

Which product identifies the management stages and timescales of a project?

A. Project Brief
B. Project Product Description
C. Project Plan
D. Initiation Stage Plan

Correct Answer: C

Prince2 Foundation Exam Test – 38

Identify the missing word in the following sentence. The purpose of the [?] theme is to identify, assess and control uncertainty.

A. Change
B. Plans
C. Quality
D. Risk

Correct Answer: D

Prince2 Foundation Exam Test – 37

Which is a purpose of quality planning?

A. Define the structure of the project management team
B. Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project’s product
C. Document approval records for those project products that have met their quality criteria
D. Produce the Project Plan with resource and schedule information

Correct Answer: B