Whose approval is needed to replace a Stage Plan with an Exception Plan?
A. Corporate or programme management
B. Project Board
C. Project Manager
D. Team Manager
Whose approval is needed to replace a Stage Plan with an Exception Plan?
A. Corporate or programme management
B. Project Board
C. Project Manager
D. Team Manager
Which is a recommended quality review team role?
A. Project Manager
B. Assurance
C. Project Support
D. Administrator
Which is a purpose of an End Project Report?
A. Identify individuals or groups that need to be told that the project is coming to an end
B. Review how well the project performed against the Project Initiation Documentation used to authorize it
C. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
D. Ensure that key project information is archived and made secure
Identify the missing words in the following sentence.
The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.
A. Project Assurance
B. Project Support
C. the risk actionee
D. the risk owner
Which is a FALSE statement about technical stages?
A. Can overlap with other technical stages
B. Typified by the use a particular set of specialist skills
C. Include the Managing a Stage Boundary process activities
D. Can span more than one management stage
Which is a purpose of the Starting up a Project process?
A. Provide information so a decision can be made as to whether a project is viable and worthwhile to initiate
B. Define the means of communication between the project and corporate or programme management
C. Define the project controls
D. Record any identified risks in the Risk Register
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
A. Only corporate or programme management
B. Only the Project Board
C. Only the Project Manager
D. All levels of management
Which is a purpose of the Risk Register?
A. Describe the risk management techniques and standards to be applied to the project
B. Act as a central record of information relating to the identified risks for the project
C. Act as a repository for informal issues
D. List the responsibilities for achieving an effective risk management procedure
Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?
A. Managing Product Delivery
B. Initiating a Project
C. Managing a Stage Boundary
D. Starting up a Project
Identify the missing word in the following sentence.
The risk response type [ ? ] can be used to respond to a threat and an opportunity
A. Avoid
B. Reduce
C. Share
D. Transfer