Prince2 Foundation Exam Test – 56

Which statement about the Directing a Project process is FALSE?

A. Supports the PRINCE2 principle of manage by exception
B. Is triggered by a request to initiate a project
C. Covers the day-to-day activities of the Project Manager
D. Provides a mechanism for the Project Board to assure that there is continued business justification

Correct Answer: C