Prince2 Foundation Exam Test – 66

Which two roles are linked by the Managing Product Delivery process?

A. Corporate or programme management and Project Board
B. Project Board and Project Manager
C. Project Manager and Team Manager
D. Team Manager and external supplier

Correct Answer: C

Prince2 Foundation Exam Test – 65

Which of the following statements about the Closing a Project process are true?

1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the
work performed in the final stage.

2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project
Initiation Documentation have been achieved. Packages for the work performed in the final stage.

A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true

Correct Answer: B

Prince2 Foundation Exam Test – 64

Which is NOT a purpose of the Organization theme?

A. Define a project management team structure
B. Define the level of tolerance for each level of the project management team
C. Define the Project Board’s responsibility for directing the project
D. Define which role is accountable for the project’s success

Correct Answer: B

Prince2 Foundation Exam Test – 63

Which of the following is NOT a purpose of the Closing a Project process?

A. Plan the activities required to close a project
B. Enable a comparison of the original objectives of a project against what was actually achieved
C. Enable premature closure if the Project Board request that a project should no longer continue
D. Provide a fixed point at which acceptance for the project product is confirmed

Correct Answer: A

Prince2 Foundation Exam Test – 62

Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.

A. minimum necessary is done to decide if a project is worthwhile
B. aim is to establish sound foundations to achieve a successful project
C. Project Brief is assembled and approved
D. project approach appropriate for delivering a project is selected

Correct Answer: B

Prince2 Foundation Exam Test – 61

Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

A. Controlling a Stage
B. Closing a Project
C. Directing a Project
D. Managing a Stage Boundary

Correct Answer: D

Prince2 Foundation Exam Test – 59

Which is a responsibility of a risk owner?

A. Identify risks to the project that might occur in their department
B. Own and authorize the use of the risk budget to fund risk responses
C. Manage, monitor and control all aspects of an assigned risk
D. Determine project risk appetite

Correct Answer: C

Prince2 Foundation Exam Test – 57

Which is a purpose of the Plans theme?

A. Identify, assess and control any potential changes to the baseline
B. Establish the project’s structure of accountability
C. Assess and control uncertainty
D. Understand whether the targets are achievable

Correct Answer: D