Prince2 Foundation Exam Test – 256

What product records any time tolerances agreed between the Project Manager and Team Manager?

A. Product Description
B. Work Package
C. Project Initiation Documentation
D. Stage Plan

Correct Answer: B

Prince2 Foundation Exam Test – 255

Identify the missing words in the following sentence.
At an agreed frequency, a Team Manager will send a [ ? ] to the Project Manager.

A. Highlight Report
B. Product Status Account
C. Checkpoint Report
D. Work Package

Correct Answer: C

Prince2 Foundation Exam Test – 254

Identify the missing words in the following sentence.
At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the
End Stage Report to external interested parties.

A. Stage Plan
B. Communication Management Strategy
C. Follow-on action recommendations
D. Quality Management Strategy

Correct Answer: B

Prince2 Foundation Exam Test – 253

Which of the following describes a use of a Configuration Item Record?

A. To record how changes to a product will be controlled
B. To provide information on the approval procedure for the Work Package
C. To record the history of a product
D. To pass responsibility for the delivery of a product to a Team Manager

Correct Answer: C

Prince2 Foundation Exam Test – 252

Which of the following are true statements about a Project Brief?

1. Used to provide a foundation for the Initiating a Project process
2. Created in the Starting up a Project process
3. Used by the Project Board to make an assessment of a project’s progress
4. Used as the basis of the Project Initiation Documentation

A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4

Correct Answer: B

Prince2 Foundation Exam Test – 251

Which is an objective of the Initiating a Project process?

A. Develop the corporate quality management system as part of the Project Initiation Documentation
B. Prepare the plans for the subsequent stages
C. Summarize how the organization’s project management method will be tailored for the project
D. Request authority from corporate management to deliver the project

Correct Answer: C

Prince2 Foundation Exam Test – 250

Which is a purpose of the Quality theme?

A. Establish how the project will ensure that all products created meet their requirements
B. Establish quality assurance to maintain the quality management system
C. Identify all the products of the project to ensure the scope has been adequately defined
D. Determine the communication needs of the organization’s quality assurance function

Correct Answer: A

Prince2 Foundation Exam Test – 249

Which does the Executive need to ensure is in place before the project is initiated?

A. All Work Packages are authorized
B. An understanding of how the project will contribute to corporate objectives
C. The Project Plan has been approved
D. The Project Initiation Documentation is complete

Correct Answer: B

Prince2 Foundation Exam Test – 248

Which is the Change Authority role permitted to authorize?

A. Risks to the project
B. Adjustments to the limits on the change budget
C. Changes to stage tolerance
D. Changes to the project that do not exceed a defined budget

Correct Answer: D

Prince2 Foundation Exam Test – 247

Which is NOT obtained from a product’s Product Description?

A. The product’s quality criteria
B. Who will approve the product
C. The quality method to be used
D. The development method to be used

Correct Answer: D