Prince2 Foundation Exam Test – 249

Which does the Executive need to ensure is in place before the project is initiated?

A. All Work Packages are authorized
B. An understanding of how the project will contribute to corporate objectives
C. The Project Plan has been approved
D. The Project Initiation Documentation is complete

Correct Answer: B