Prince2 Foundation Exam Test – 265

Which is performed as part of the recommended risk management procedure?

A. Allocation of a budget to investigate issues facing the project
B. Review of risk management practices to ensure that they are performed effectively
C. Sending of information about risks to the project to project stakeholders
D. Resolution of conflicts between the project and the programme board

Correct Answer: C

Prince2 Foundation Exam Test – 264

Identify the missing words in the following sentence.
Configuration management typically includes [ ? ] as one of the five core activities.

A. exception planning
B. risk assessment
C. stakeholder engagement
D. status accounting

Correct Answer: D

Prince2 Foundation Exam Test – 263

Which is a purpose of the Closing a Project process?

A. Authorize the final stage of the project
B. Confirm that all benefits defined in the Business Case have been achieved
C. Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
D. Delegate day-to-day management of the end of the project to the Project Manager

Correct Answer: C

Prince2 Foundation Exam Test – 262

Which is a purpose of an Issue Report?

A. Provide the status of all issues in a Work Package
B. Document an issue that needs to be handled formally
C. Provide the status of all the issues in a stage
D. Notify the Project Manager of all new issues in a Work Package

Correct Answer: B

Prince2 Foundation Exam Test – 261

Which describes risk appetite?

A. An organization’s unique attitude towards risk-taking
B. The risks to the expected benefits
C. A common set of risk categories, risk scales and evaluation techniques
D. The budget set aside for potential changes to the scope of the project

Correct Answer: A

Prince2 Foundation Exam Test – 259

Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

A. Corporate group
B. Project Board
C. Project Assurance
D. Executive

Correct Answer: A

Prince2 Foundation Exam Test – 258

What product is used to maintain a record of those who have an interest in the project and their information requirements?

A. Project Plan
B. Communication Management Strategy
C. Project Brief
D. Project Product Description

Correct Answer: B

Prince2 Foundation Exam Test – 257

Which is part of quality control?

A. Document the project’s acceptance criteria in the Project Product Description
B. Define the quality responsibilities of those involved in the production of the products
C. Produce quality records to show that the planned quality activities have been carried out
D. Maintain the corporate organization’s quality management system

Correct Answer: C