Prince2 Foundation Exam Test – 116

Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

A. Those with a financial interest in the project
B. Those who will manage the project on a day-to-day basis
C. Those who will specify the desired outputs of the project
D. Those who will create the project’s outputs

Correct Answer: B

Prince2 Foundation Exam Test – 115

Which is NOT a purpose of the Initiating a Project process?

A. Enable a Project Board decision about the commitment of resources to a project
B. Enable an organization to understand the work that needs to be done to deliver a project’s products before
a project is approved
C. Establish solid foundations for a project
D. Enable the Project Board to decide whether it is worthwhile to initiate a project

Correct Answer: D

Prince2 Foundation Exam Test – 114

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

A. Project Brief
B. Project Initiation Documentation
C. Project mandate
D. Benefits Review Plan

Correct Answer: B

Prince2 Foundation Exam Test – 113

Which is an objective of the Directing a Project process?

A. Create and authorize the project mandate
B. Provide management control and direction
C. Control the day-to-day running of the project
D. Provide accurate progress information to the Project Manager

Correct Answer: B

Prince2 Foundation Exam Test – 112

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

A. Create a separate Project Board to manage the supplier elements of the project
B. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project’s stages.
C. Create user and supplier groups
D. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project
Board

Correct Answer: C

Prince2 Foundation Exam Test – 111

Which is a typical core activity within configuration management?

A. Issue management
B. Quality inspection
C. Quality inspection
D. Preparation

Correct Answer: C

Prince2 Foundation Exam Test – 110

Which plan provides the Business Case with costs during the Initiating a Project process?

A. Initiation Stage Plan
B. Project Plan
C. Stage Plan
D. Team Plan

Correct Answer: B

Prince2 Foundation Exam Test – 108

Who should act as the communication channel between a project and corporate or programme management?

A. Project Board
B. Project Assurance
C. Project Manager
D. Project Support

Correct Answer: A

Prince2 Foundation Exam Test – 107

Which statement about the Directing a Project process is true?

A. Provides a mechanism for the Project Board to assure that there is continued business justification
B. Covers the day-to-day activities of the Project Manager
C. Ensures there are regular progress meetings
D. Begins on completion of the Initiating a Project process

Correct Answer: A