Prince2 Foundation Exam Test – 114

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

A. Project Brief
B. Project Initiation Documentation
C. Project mandate
D. Benefits Review Plan

Correct Answer: B