Which statement about the Directing a Project process is true?

A. Provides a mechanism for the Project Board to assure that there is continued business justification
B. Covers the day-to-day activities of the Project Manager
C. Ensures there are regular progress meetings
D. Begins on completion of the Initiating a Project process

Correct Answer: A