What is used to identify any organization or interested party who needs to be informed of project closure?
A. Configuration Management Strategy
B. Project management team structure
C. Communication Management Strategy
D. Project Brief
What is used to identify any organization or interested party who needs to be informed of project closure?
A. Configuration Management Strategy
B. Project management team structure
C. Communication Management Strategy
D. Project Brief
Which products, identified when creating a product breakdown structure, should each have a corresponding entry in the Risk Register?
A. Those that have been completed, but have NOT been quality checked
B. Those that have been broken down into sub-products
C. Those to be created outside the scope of the project
D. Those dependent on more than one other product
Which is a purpose of the Directing a Project process?
A. Provide the information required to confirm if it is worthwhile to initiate a project
B. Enable overall control of a project to be exercised by the Project Board
C. Establish the level of control required by the Project Board after initiation
D. Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved
Which is NOT a PRINCE2 principle?
A. Learn from experience
B. Customer/supplier environment
C. Defined roles and responsibilities
D. Continued business justification
Which is NOT a benefit of using PRINCE2?
A. Defines specific leadership, motivational skills and other interpersonal skills required
B. Can be applied to any type of project
C. Promotes learning and continuous improvement
D. Defines a thorough but economical structure of reports
Which statement applies to Stage Plans?
A. Always have the same duration as the Project Plan
B. Are produced at the same time as the Project Initiation Documentation
C. Assist the Project Manager in the day-to-day running and control of the project
D. Provide a baseline against which the Project Board monitor overall progress
What theme establishes the mechanisms to judge whether a project is worthwhile investing in?
A. Plans
B. Business Case
C. Risk
D. Quality
Which of the following are objectives of the Directing a Project process?
1. Ensure corporate or programme management has an interface to a project
2. Ensure that work on products allocated to a team is authorized
3. Ensure there is authority to initiate a project
4. Ensure that a project remains viable
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
A. Raise a request for change
B. Raise an off-specification
C. Write an Exception Report
D. Amend the Work Package
Identify the missing words in the following sentence.
When planning the next stage, the Project Manager needs to review and, if necessary, update the [ ? ] with regard to external resources or suppliers.
A. Configuration Item Records
B. Business Case
C. Project Brief
D. project management team and/or role descriptions