Which role does NOT set tolerances?
A. Corporate or programme management
B. Project Board
C. Change Authority
D. Project Manager
Which role does NOT set tolerances?
A. Corporate or programme management
B. Project Board
C. Change Authority
D. Project Manager
Identify the missing product in the following sentence.
When assessing an issue during the Controlling a Stage process, the [ ? ] provides essential information to evaluate the viability of the project.
A. Project Brief
B. Benefits Review Plan
C. Project Initiation Documentation
D. Configuration Management Strategy
Which of the following is NOT part of quality control?
A. Maintaining the documentation that records the approval of products
B. Checking that the project’s direction and management are adequate for the nature of the project
C. Obtaining acceptance of the project product from relevant stakeholders
D. Implementing the relevant quality methods and responsibilities
Which is a purpose of the Controlling a Stage process?
A. Assign work to be done and take corrective action to ensure that the stage remains within tolerance
B. Provide a fixed reference point at which acceptance for the project product is confirmed
C. Enable the Project Board to be provided with sufficient information to authorize the next stage
D. Enable the organization to understand the work that needs to be done to deliver the project’s products
Which risk response type is a recommended response to both an opportunity and a threat?
A. Avoid
B. Reduce
C. Share
D. Reject
Which is a PRINCE2 time-driven control?
A. End Stage Report
B. Project Brief
C. Project Initiation Documentation
D. Checkpoint Report
Which may be funded from a risk budget?
A. Capturing identified threats and opportunities in the Risk Register
B. Specific management responses to a project’s threats and opportunities
C. Producing risk summaries for inclusion in Highlight Reports
D. Any remaining open risks after the project has been closed
Identify the missing word(s) in the following sentence.
During a quality review meeting [ ? ] any identified defects.
A. a solution should be designed for
B. an issue should be created for
C. the agreed actions should be recorded for
D. the chair will approve the solution to
What is a purpose of a Benefits Review Plan?
A. Provide information regarding unfinished work to the group which will support the project’s products in their operational life
B. Give a detailed analysis of only those benefits that were realized before the project closed
C. Document the justification for undertaking the project, based on the estimated costs versus the anticipated benefits
D. Provide details of the time and effort needed to carry out the planned benefits reviews
Which describes a risk effect?
A. The uncertainty expressed as a negative or favourable occurrence
B. The issue which is affecting the project and has resulted in a risk
C. The impact(s) on the project objectives should the threat or opportunity occur
D. The change in the status of a risk in response to actions taken to control it