Prince2 Foundation Exam Test – 205

Which products, identified when creating a product breakdown structure, should each have a corresponding entry in the Risk Register?

A. Those that have been completed, but have NOT been quality checked
B. Those that have been broken down into sub-products
C. Those to be created outside the scope of the project
D. Those dependent on more than one other product

Correct Answer: C