Prince2 Foundation Exam Test – 284

How many management stages should a PRINCE2 project consist of?

A. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
B. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
C. Initiation stage and at least one other management stage to cover the remainder of the project
D. Start up stage, initiation stage and a closing stage

Correct Answer: C

Prince2 Foundation Exam Test – 283

Identify the missing words in the following sentence.
A Project Manager agrees the [ ? ] with a Team Manager.

A. project cost tolerance
B. stage cost tolerance
C. Work Package cost tolerance
D. product cost tolerance

Correct Answer: C

Prince2 Foundation Exam Test – 281

Identify the missing words in the following sentence.
The [ ? ] should include representation to satisfy the interests of the three primary categories of stakeholders affected by a PRINCE2 project.

A. Corporate or programme management
B. Project Board
C. Team Managers
D. Project Support

Correct Answer: B

Prince2 Foundation Exam Test – 279

What do customer’s quality expectations identify?

A. Standards that must be used in order to meet the level of quality needed
B. Skills required to develop the project product
C. Measurable definitions of the attributes required for a set of products to be acceptable to the customer
D. Reviewer names for each product

Correct Answer: A