Prince2 Foundation Exam Test – 293

Identify the missing words in the following sentence.
The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.

A. Project Assurance
B. Project Support
C. the risk actionee
D. the risk owner

Correct Answer: C