Prince2 Foundation Exam Test – 283

Identify the missing words in the following sentence.
A Project Manager agrees the [ ? ] with a Team Manager.

A. project cost tolerance
B. stage cost tolerance
C. Work Package cost tolerance
D. product cost tolerance

Correct Answer: C