Prince2 Foundation Exam Test – 286

Which is a task of product-based planning?

A. Identify activities and dependencies
B. Write the Project Product Description
C. Prepare the Work Packages
D. Produce Product Status Accounts

Correct Answer: B

Prince2 Foundation Exam Test – 284

How many management stages should a PRINCE2 project consist of?

A. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
B. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
C. Initiation stage and at least one other management stage to cover the remainder of the project
D. Start up stage, initiation stage and a closing stage

Correct Answer: C

Prince2 Foundation Exam Test – 283

Identify the missing words in the following sentence.
A Project Manager agrees the [ ? ] with a Team Manager.

A. project cost tolerance
B. stage cost tolerance
C. Work Package cost tolerance
D. product cost tolerance

Correct Answer: C

Prince2 Foundation Exam Test – 282

What is described as an organization’s unique attitude towards risk taking?

A. Risk appetite
B. Risk management
C. Risk evaluation
D. Risk tolerance

Correct Answer: A

Prince2 Foundation Exam Test – 281

Identify the missing words in the following sentence.
The [ ? ] should include representation to satisfy the interests of the three primary categories of stakeholders affected by a PRINCE2 project.

A. Corporate or programme management
B. Project Board
C. Team Managers
D. Project Support

Correct Answer: B

Prince2 Foundation Exam Test – 279

What do customer’s quality expectations identify?

A. Standards that must be used in order to meet the level of quality needed
B. Skills required to develop the project product
C. Measurable definitions of the attributes required for a set of products to be acceptable to the customer
D. Reviewer names for each product

Correct Answer: A

Prince2 Foundation Exam Test – 277

Which product records any project outcomes perceived as negative by stakeholders?

A. Business Case
B. Project Plan
C. Communication Management Strategy
D. Project Product Description

Correct Answer: A