Which is a task of product-based planning?
A. Identify activities and dependencies
B. Write the Project Product Description
C. Prepare the Work Packages
D. Produce Product Status Accounts
Which is a task of product-based planning?
A. Identify activities and dependencies
B. Write the Project Product Description
C. Prepare the Work Packages
D. Produce Product Status Accounts
Which role is responsible for creating Checkpoint Reports?
A. Senior Supplier
B. Team Manager
C. Change Authority
D. Project Support
How many management stages should a PRINCE2 project consist of?
A. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
B. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
C. Initiation stage and at least one other management stage to cover the remainder of the project
D. Start up stage, initiation stage and a closing stage
Identify the missing words in the following sentence.
A Project Manager agrees the [ ? ] with a Team Manager.
A. project cost tolerance
B. stage cost tolerance
C. Work Package cost tolerance
D. product cost tolerance
What is described as an organization’s unique attitude towards risk taking?
A. Risk appetite
B. Risk management
C. Risk evaluation
D. Risk tolerance
Identify the missing words in the following sentence.
The [ ? ] should include representation to satisfy the interests of the three primary categories of stakeholders affected by a PRINCE2 project.
A. Corporate or programme management
B. Project Board
C. Team Managers
D. Project Support
Who does the Team Manager report to and take direction from?
A. Project Board
B. Project Assurance
C. Project Manager
D. Project Support
What do customer’s quality expectations identify?
A. Standards that must be used in order to meet the level of quality needed
B. Skills required to develop the project product
C. Measurable definitions of the attributes required for a set of products to be acceptable to the customer
D. Reviewer names for each product
Which product is used by the Project Manager to authorize work?
A. Team Plan
B. Stage Plan
C. Work Package
D. Product Description
Which product records any project outcomes perceived as negative by stakeholders?
A. Business Case
B. Project Plan
C. Communication Management Strategy
D. Project Product Description