Who carries out audits that are independent of the project?
A. Quality assurance
B. Project Assurance
C. Project Support
D. Project Manager
Who carries out audits that are independent of the project?
A. Quality assurance
B. Project Assurance
C. Project Support
D. Project Manager
Which is a purpose of a Project Brief?
A. Enable the assembly of the project mandate
B. Describe the reporting requirements of the various layers of management involved with the project
C. Describe how changes to products will be controlled
D. Provide a solid basis for the initiation of the project
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
A. Change
B. Cross-functional
C. Unique
D. Risk
What takes place during the Closing a Project process?
A. The post-project benefits reviews are performed
B. Ownership of the project’s products is transferred to the customer
C. An End Stage Report is prepared for the final stage
D. The project closure notification is reviewed and approved
Which is a purpose of a Configuration Management Strategy?
A. Provide a record of each configuration item and any important relationships between them
B. Define how the products and their versions will be identified
C. Define whether a project will use a risk budget
D. Identify who will set up the Quality Register
Which is created during the Starting up a Project process?
A. Project mandate
B. Project management team role descriptions
C. Communication Management Strategy
D. Quality Register
Which activity takes place within the Managing a Stage Boundary process?
A. Produce Highlight Reports
B. Take corrective action within the limits of a stage’s tolerance
C. Produce an Exception Plan
D. Authorize a Stage Plan for the next stage
What product forms the contract’ between the Project Board and the Project Manager?
A. Project Brief
B. Project Initiation Documentation
C. Project mandate
D. Project Plan
Which is a purpose of a Risk Register?
A. Capture risks that may occur during the project
B. Record how risk management activities will be undertaken on the project
C. Record the risk tolerance for the project
D. Capture issues which are impacting on the delivery of the project objectives
Which is an objective of the Starting up a Project process?
A. Approve all Product Descriptions prior to project initiation
B. Obtain approval from corporate or programme management for the Communication Management Strategy
C. Prevent projects with unrealistic delivery dates from being initiated
D. Confirm that there is a valid method in place to measure the expected project benefits