Prince2 Foundation Exam Test – 26

Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?

A. Principles
B. Processes
C. Tailoring PRINCE2 to the project environment
D. Themes

Correct Answer: A

Prince2 Foundation Exam Test – 25

Which process provides the Project Board with the information it requires in order to commit resources to the project?

A. Managing Product Delivery
B. Initiating a Project
C. Controlling a Stage
D. Directing a Project

Correct Answer: B

Prince2 Foundation Exam Test – 24

Identify the missing word in the following sentence, A project’s output is produced during a project but the [?] for the project are often only realized after the project has closed.

A. costs
B. risks
C. benefits
D. issues

Correct Answer: C

Prince2 Foundation Exam Test – 23

Which task is performed by the Change Authority?

A. Set a change budget
B. Approve or reject a request for change within approved limits
C. Refer changes that exceed budgetary limits to the Project Manager for approval
D. Update the configuration management system when a change is approved

Correct Answer: B

Prince2 Foundation Exam Test – 22

Identify the missing words in the following sentence, The six aspects of project performance to be managed are [?] costs, timescales and scope.

A. benefits, progress, risk,
B. benefits, quality, risk,
C. change, quality, progress,
D. benefits, customers, quality,

Correct Answer: B

Prince2 Foundation Exam Test – 20

Which is part of the PRINCE2 definition of a project?

A. An undertaking that consists of at least two management stages
B. A description of what must be delivered in order to gain acceptance
C. The total of a plan’s products
D. A temporary organization that is created for the purpose of delivering business products

Correct Answer: D

Prince2 Foundation Exam Test – 19

Which is a purpose of the Risk theme?

A. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
B. Establish a cost-effective procedure to identify, assess and control uncertainty
C. Establish mechanisms to control any unacceptable deviations from plan
D. Establish mechanisms to manage risks at the corporate or programme level of an organization

Correct Answer: B

Prince2 Foundation Exam Test – 18

If a project’s benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

A. Senior User
B. Executive
C. Corporate/programme management
D. Senior Supplier

Correct Answer: C

Prince2 Foundation Exam Test – 17

Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,

A. Management strategies
B. Plan
C. Stakeholder interests
D. Time-driven controls

Correct Answer: B