Prince2 Foundation Exam Test – 23

Which task is performed by the Change Authority?

A. Set a change budget
B. Approve or reject a request for change within approved limits
C. Refer changes that exceed budgetary limits to the Project Manager for approval
D. Update the configuration management system when a change is approved

Correct Answer: B

Prince2 Foundation Exam Test – 20

Which is part of the PRINCE2 definition of a project?

A. An undertaking that consists of at least two management stages
B. A description of what must be delivered in order to gain acceptance
C. The total of a plan’s products
D. A temporary organization that is created for the purpose of delivering business products

Correct Answer: D

Prince2 Foundation Exam Test – 19

Which is a purpose of the Risk theme?

A. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
B. Establish a cost-effective procedure to identify, assess and control uncertainty
C. Establish mechanisms to control any unacceptable deviations from plan
D. Establish mechanisms to manage risks at the corporate or programme level of an organization

Correct Answer: B