Prince2 Foundation Exam Test – 136

Which is an objective of the Controlling a Stage process?

A. Prepare a Stage Plan for the next stage
B. Obtain approvals for completed products
C. Prevent scope creep’ by monitoring products for uncontrolled change
D. Make arrangements to address all open issues and risks, with follow-on action recommendations

Correct Answer: C

Prince2 Foundation Exam Test – 134

Identify the missing words in the following sentence. The purpose of the Starting up a Project process is as much about [?] as it is about requesting authorization to initiate viable projects,

A. producing an achievable Project Plan
B. preventing poorly-conceived projects from ever being initiated
C. obtaining approval from all stakeholders
D. setting up the required project controls

Correct Answer: B

Prince2 Foundation Exam Test – 133

Which is a true statement about management stages and technical stages?

A. Technical stages can overlap but management stages CANNOT
B. Management stages are the responsibility of the Project Manager, technical stages are NOT
C. Technical stages create products, management stages do NOT
D. Management stages require quality control, technical stages do NOT

Correct Answer: A

Prince2 Foundation Exam Test – 132

Which is a purpose of an Exception Plan?

A. Show the reason for the tolerance deviation from a Stage Plan or Project Plan
B. Reduce the number of exception assessments, by agreeing a budget to cover the costs of any requests for change
C. Identify the actions required to recover from the effect of a tolerance deviation
D. Define the changes which are within the scope of the change budget

Correct Answer: C

Prince2 Foundation Exam Test – 131

Which is a purpose of the Risk theme?

A. Establish a method for the implementation of continuous improvement during the project
B. Identify, assess and control problems that have occurred
C. Provide the Project Board with a time-driven control to capture all project risks
D. Establish a cost-effective procedure to identify, assess and control risks

Correct Answer: D