Prince2 Foundation Exam Test – 134

Identify the missing words in the following sentence. The purpose of the Starting up a Project process is as much about [?] as it is about requesting authorization to initiate viable projects,

A. producing an achievable Project Plan
B. preventing poorly-conceived projects from ever being initiated
C. obtaining approval from all stakeholders
D. setting up the required project controls

Correct Answer: B