Prince2 Foundation Exam Test – 55

What process is used by the Project Manager to maintain focus on delivery of a stage’s products within agreed tolerances?

A. Directing a Project
B. Controlling a Stage
C. Managing a Stage Boundary
D. Managing Product Delivery

Correct Answer: B