Which is NOT one of the levels of plan recommended by PRINCE2?
A. Benefits Review Plan
B. Project Plan
C. Stage Plan
D. Team Plan
Which is NOT one of the levels of plan recommended by PRINCE2?
A. Benefits Review Plan
B. Project Plan
C. Stage Plan
D. Team Plan