Which is a purpose of the Directing a Project process?
A. Provide the information required to confirm if it is worthwhile to initiate a project
B. Enable overall control of a project to be exercised by the Project Board
C. Establish the level of control required by the Project Board after initiation
D. Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved