Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
A. Off-specifications
B. Follow-on action recommendations
C. Issue Register
D. Risk Register
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
A. Off-specifications
B. Follow-on action recommendations
C. Issue Register
D. Risk Register