Prince2 Foundation Exam Test – 226

Identify the missing word in the following sentence.
The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

A. Principles
B. Themes
C. Processes
D. Techniques

Correct Answer: A

Prince2 Foundation Exam Test – 225

Which is NOT one of the PRINCE2 integrated elements?

A. Tailoring PRINCE2 to the project environment
B. The processes
C. The products
D. The themes

Correct Answer: C

Prince2 Foundation Exam Test – 224

From whom does a Team Manager obtain approval for a completed product?

A. Project Manager
B. Project Support
C. The authority defined in the Product Description
D. Senior Supplier

Correct Answer: C

Prince2 Foundation Exam Test – 222

Which aspect of project performance must be managed to ensure the project’s products are fit for purpose?

A. Benefits
B. Quality
C. Risk
D. Scope

Correct Answer: B

Prince2 Foundation Exam Test – 221

Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?

A. Capture
B. Examine
C. Propose
D. Decide

Correct Answer: C

Prince2 Foundation Exam Test – 220

Which is the Issue Register NOT used for?

A. Capture external events that are impacting a stage
B. Record information about a deviation in stage tolerance
C. Capture any threats or opportunities that might have an impact on a stage
D. Record any problems identified when authorizing a Work Package

Correct Answer: C

Prince2 Foundation Exam Test – 219

Which process covers the work done by external suppliers who may NOT be using PRINCE2?

A. Closing a Project
B. Managing a Stage Boundary
C. Managing Product Delivery
D. Directing a Project

Correct Answer: C

Prince2 Foundation Exam Test – 218

What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

A. Team Plan
B. Stage Plan
C. Benefits Review Plan
D. Project Plan

Correct Answer: B

Prince2 Foundation Exam Test – 217

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

A. Manage by stages
B. Manage by exception
C. Continued business justification
D. Learn from experience

Correct Answer: B