Prince2 Foundation Exam Test – 246

Which is NOT a true statement about the Managing a Stage Boundary process?

A. It provides sufficient information for the Project Board to review the success of the current stage
B. It is used to create an Exception Plan if requested by the Project Board
C. It provides a fixed point at which acceptance of the project product is confirmed
D. It is executed at, or close to, the end of each management stage, except the final one

Correct Answer: C

Prince2 Foundation Exam Test – 245

In which product would you find a product’s quality tolerance defined?

A. Product Description
B. Quality Management Strategy
C. Quality Register
D. Configuration Item Record

Correct Answer: A

Prince2 Foundation Exam Test – 243

Which is a purpose of the Directing a Project process?

A. Create and authorize the project mandate
B. Ensure that work on products allocated to the team is authorized and agreed
C. Control the day-to-day running of the project
D. Delegate day-to-day management of the project to the Project Manager

Correct Answer: D

Prince2 Foundation Exam Test – 242

Why would the Project Manager escalate an issue to the Project Board?

A. The Project Board is responsible for determining the priority of all issues
B. Direction is required on the best response for preventing the issue from occurring
C. The issue is forecast to cause a deviation beyond stage tolerance and advice is required
D. Escalating issues is a means of providing the Project Board with a regular update on their status

Correct Answer: C

Prince2 Foundation Exam Test – 241

Which of the following are typical core activities within configuration management?

1. Planning
2. Risk assessment
3. Verification and audit
4. Identification

A. 1, 2, 3
B. 1, 2, 4
C. 1, 3 ,4
D. 2, 3, 4

Correct Answer: C

Prince2 Foundation Exam Test – 239

Which is a purpose of a Lessons Log?

A. Note any lessons that are raised in Checkpoint Reports
B. Record that corrective action is being taken
C. Escalate lessons to the Project Board
D. Raise improvements with Project Assurance

Correct Answer: A

Prince2 Foundation Exam Test – 238

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

A. Configuration Item Record
B. Quality Register
C. Highlight Report
D. Checkpoint Report

Correct Answer: D

Prince2 Foundation Exam Test – 237

Which is a true statement about PRINCE2 event-driven controls

A. Event-driven controls take place at predefined periodic intervals
B. Event-driven controls are produced at the frequency defined in a Work Package
C. Event-driven controls are used for decision making
D. Checkpoint Reports are event-driven controls

Correct Answer: C