Which is an objective of the Managing a Stage Boundary process?
A. Understand what has gone well and what can help the next stage
B. Review and approve the next Stage Plan
C. Assure the Project Board that all project products have been completed and approved
D. Prepare an Exception Report to advise the Project Board of a forecast deviation from tolerance