Which of the following is NOT a purpose of the Closing a Project process?
A. Plan the activities required to close a project
B. Enable a comparison of the original objectives of a project against what was actually achieved
C. Enable premature closure if the Project Board request that a project should no longer continue
D. Provide a fixed point at which acceptance for the project product is confirmed