Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.
A. minimum necessary is done to decide if a project is worthwhile
B. aim is to establish sound foundations to achieve a successful project
C. Project Brief is assembled and approved
D. project approach appropriate for delivering a project is selected