Prince2 Foundation Exam Test – 34

Which statement is FALSE?

A. A project outcome perceived to be negative by one or more stakeholders is a dis-benefit
B. A project’s output is any of the project’s specialist products
C. A project benefit is only realized after the project has closed
D. A project outcome is the result of the change derived from using the project’s outputs

Correct Answer: C