Prince2 Foundation Exam Test – 179 Which is a type of issue? A. An expected dis-benefit B. An off-specification C. A project outcome D. A scope tolerance Show Answer Correct Answer: B Post navigation Prince2 Foundation Exam Test – 178Prince2 Foundation Exam Test – 180