Identify the missing word(s) in the following sentence. Quality assurance provides assurance to the [?] that the project is being conducted appropriately whilst Project Assurance provides the same assurance to all the project’s stakeholders.
A. Project Manager
B. Executive
C. corporate or programme management organization
D. Supplier groups