Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

A. Create a separate Project Board to manage the supplier elements of the project
B. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project’s stages.
C. Create user and supplier groups
D. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project
Board

Correct Answer: C