Which is NOT an objective of the Controlling a Stage process?
A. Implement actions to control the impact of risks that occur during the stage
B. Review the Business Case at regular intervals to assess the impact of changes that occur during the stage
C. Update the Business Case with any changes agreed with the Project Board
D. Coordinate the delivery of products as agreed in the Stage Plan