Prince2 Foundation Exam Test – 94

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

A. Only corporate or programme management
B. Only the Project Board
C. Only the Project Manager
D. All levels of management

D. All levels of management