Prince2 Foundation Exam Test – 81

When are tolerances for a Work Package agreed?

A. When accepting a Work Package
B. As work on each product within the Work Package begins
C. Once ail products have been developed and approved
D. When the Stage Plan is authorized by the Project Board

Correct Answer: A