Prince2 Foundation Exam Test – 74

Which of the following is the Business Case used for during the Managing a Stage Boundary process?

A. Enable the Project Board to decide whether or not to authorize the project
B. Justify the continuing viability of the project
C. Enable the Project Board to decide whether or not to authorize project closure
D. Justify the initiation of a project

Correct Answer: B