Prince2 Foundation Exam Test – 65

Which of the following statements about the Closing a Project process are true?

1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the
work performed in the final stage.

2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project
Initiation Documentation have been achieved. Packages for the work performed in the final stage.

A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true

Correct Answer: B