Prince2 Foundation Exam Test – 198

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

A. Raise a request for change
B. Raise an off-specification
C. Write an Exception Report
D. Amend the Work Package

Correct Answer: B