Prince2 Foundation Exam Test – 181

Which process is used by a Team Manager to coordinate work on one or more of the project’s products?

A. Initiating a Project
B. Controlling a Stage
C. Managing a Stage Boundary
D. Managing Product Delivery

Correct Answer: D