Prince2 Foundation Exam Test – 131

Which is a purpose of the Risk theme?

A. Establish a method for the implementation of continuous improvement during the project
B. Identify, assess and control problems that have occurred
C. Provide the Project Board with a time-driven control to capture all project risks
D. Establish a cost-effective procedure to identify, assess and control risks

Correct Answer: D