Prince2 Foundation Exam Test – 103

Which process is triggered towards the end of the final stage when all the assigned work has been completed?

A. Managing a Stage Boundary
B. Managing Product Delivery
C. Closing a Project
D. Controlling a Stage

Correct Answer: C